Intelligent Battery Backup Unit
Manual No. 771971 B-5
Installation
Mechanical Installation Procedure
Tools Needed
The only tool needed for the installation is a small, flat-blade screwdriver
Procedure
1. If the DAC960PG is not already removed from the system, power the
system down and then remove the DAC960PG.
2. Remove the loopback plug from J5 on the DAC960PG. Keep the
loopback plug in a safe place, in case the IBBU needs to be removed at
a later time.
Figure B-2. Removing the Loopback Plug from J5 on the DAC960PG