Mylex eXtremeRAID Guia de Instalação Página 172

  • Descarregar
  • Adicionar aos meus manuais
  • Imprimir
  • Página
    / 210
  • Índice
  • MARCADORES
  • Avaliado. / 5. Com base em avaliações de clientes
Vista de página 171
Battery Backup Unit Monitoring and Maintenance
5-56 GAM Client v3.00 and WSAM Users Manual
has been subjected to a power outage, recharging may be necessary and may
take several hours.
The system administrator must initiate the condition cycle manually. The
condition cycle must complete without an interruption of power. In addition,
the operator must not interrupt the cycle by initiating a fast charge or another
condition cycle. If the cycle is interrupted for any reason, the batteries must
be recharged and the recondition process must be restarted.
Note
During the reconditioning, write back cache mode
will be disabled. This may slow normal operations.
Therefore, schedule this operation accordingly.
To ensure that the battery is fully charged and properly conditioned:
1. Choose Intelligent BBU from the Administration menu if the BBU
dialog box is not currently displayed.
2. Make sure the % Charge Level is 100. If the battery is currently
charging, do NOT continue until the Charge Level is 100.
3. Under Actions, select Recondition Battery, then click Apply.
Note
Do not interrupt the reconditioning process.
Vista de página 171
1 2 ... 167 168 169 170 171 172 173 174 175 176 177 ... 209 210

Comentários a estes Manuais

Sem comentários